| DOE-STD-1082-94
The changes to the implementation plan shall be clearly indicated (e.g.,
sidebars) to facilitate timely review. Revised plans are to be submitted to DOE
in the manner described in section 4 above and reviewed and approved in the
manner described in section 5 above.
Any changes to implementation plans which will result in a requirement not
being met require an approved exemption.
7. EXTENSIONS TO THE SUBMITTAL SCHEDULE FOR IMPLEMENTATION
PLANS
An implementing organization may request an extension to the time allowed to
prepare and submit an implementation plan through the Operations Office
point-of-contact. The Operations Office point-of-contact will coordinate the
approval or rejection of an extension request with the appropriate CSOs.
Requests for extension shall be submitted within sufficient time for DOE to
review and approve the extension before the original due date. Extensions will
be granted only for good cause, such as the complexity of the plan or the
impact of multiple plans on an implementing organization's resources. Such
requests should be drafted as narrowly as possible to permit timely compliance
with as many nuclear safety requirements as possible.
An exemption is required to extend any schedule mandated in the DOE
requirements documents unless specific provisions for schedular relief are
provided.
8. IMPLEMENTATION TRACKING
Following approval of the plan and during the implementation process, the
DOE Operations Office shall oversee the contractor's progress in meeting the
commitments in the implementation plan (for example, schedules, milestones,
and costs) and maintain a dialogue on any problems that arise.