| ||||||||||
| 
 
  | ![]() DOE-STD-1134-99 
II. GUIDANCE KEYED TO SECTIONS IN DOE-STD-3007-93 
1.0 Introduction 
This introductory material is very general in nature and not of technical consequence. It should 
contain enough information to let the reviewer know why the evaluation was performed. The 
introduction should also contain a statement of what is being evaluated. This section has no 
safety significance and no technical comments should ensue from a review. 
2.0 Description 
This section must contain sufficient descriptive technical detail to understand and reconstruct the 
system being analyzed. The description of the operation should include drawings or sketches 
sufficient to allow the reviewer to make a determination that the model and analysis assumptions 
apply to the system described herein. If the system is complex, drawings and documents may be 
included by reference (e.g., an approved, field verified, process description). The key question 
for the reviewer to ask is, "From reading this section can I get a good picture of what's being 
evaluated?" If the answer is no, then deficiencies exist. The deficiencies must be resolved. 
As a rule of thumb, personnel familiar with the system under analysis should perform technical 
reviews of CSEs. At a minimum, the reviewer should possess enough knowledge of the 
system/process being analyzed to independently judge the accuracy of the process description 
(PD) insofar as it impacts the safety conclusions contained in the CSE. If the reviewer is not 
familiar with the system, facility walk-downs and discussions with the SME should be performed 
prior to completing the review. In the absence of system knowledge, all a reviewer can state is 
that the evaluator did indeed analyze what was purported to be analyzed (i.e., the CSE is 
internally consistent). 
Discrepancies in the system description are likely to be in the area of disagreements with the 
model assumptions and the "as built, as found" condition in the facility. These will only be 
discovered by facility walk-downs. Before walk-downs are initiated, a determination of the 
sensitivity of the reactivity of the system to changes in parameters should be made. The 
determination should be made by whatever means deemed prudent by the reviewer. In most 
cases, this determination will be the technical judgment of the reviewer based on his experience 
and knowledge. For example, if the model shows worst case full flooding of a glovebox remains 
subcritical, the safety of the system does not depend on the presence or absence of a criticality 
drain. On the other hand, if analysis shows greater than 2" of solution on the floor of the 
glovebox goes critical, then the presence of a functioning criticality drain is essential. Both the 
requirement of the drain and for regular inspection of the drain should be clearly identified in the 
evaluation and a walkdown performed to verify this attribute. Another example is annular 
solution storage tanks. The thickness of the annulus must be nominally the same as that assumed 
by the evaluation. However, the height of the tank does not significantly affect the reactivity of 
2 
 | 
| 
 
 Privacy Statement - Press Release - Copyright Information. - Contact Us  |