| DOE-STD-3003-2000
12)
For safety reasons, a person shall not work alone. At least two persons (Two Man Rule)
must always be present when working on electrical power systems.
PROCEDURE
A. PREPARATION
CHECK
1)
Read the following PROCESS SIGNIFICANCE statement:
Statement of battery function and significance ....
____
2)
Check to ensure that this is the latest approved revision of this procedure.
____
3)
Confirm each Instrument has a current calibration sticker and record the
information in the Instrument/Tool Report (No._____) attached to this
procedure and in the TOOLS/INSTRUMENTS/ MATERIALS Section of this
procedure.
____
4)
Obtain an authorized Work Request (No._____) and record the number on
Page 1 and Data Sheet 1 of this procedure.
____
5)
Obtain an approved Work Clearance Permit (No._____) per Site Safety
Manual.
____
6)
Confirm that the Battery Room ventilation system is operating.
____
7)
Confirm with Operations that the battery has been on normal float voltage
(XXX-XXX Vdc) for at least 72 hours since the conclusion of the last
equalization charge and subsequent return to float voltage. If not on float
charge, notify (Operations and Electrical) supervision.
____
Section A completed by ______________________________________________
/
(signature)
(print name)
Date/Time Completed ____________________________ a.m./p.m.
/
: