Each of the core requirements listed below, as a minimum, must be addressed when developing the
breadth of an Operational Readiness Review (ORR). Justification shall be provided in the plan-of-action
if it is determined that a particular core requirement will not be reviewed. The plan-of-action may
reference a timely, independent review which addressed the requirements in a technically sound manner to
justify not performing further evaluation of a core requirement during conduct of an ORR. A graded
approach, defined in Appendix 1, will be used to determine the level of analysis, documentation, and/or
actions necessary (depth) to evaluate the core requirements listed below or other core requirements in the
defined breadth of the ORR.
Minimum Core Requirements
1. There are adequate and correct procedures and safety limits for operating the process systems and
utility systems;
2. Training and qualification programs for operations and operations support personnel have been
established, documented, and implemented (the training and qualification program encompasses the
range of duties and activities required to be performed);
3. Level of knowledge of operations and operations support personnel is adequate based on reviews of
examinations and examination results, and selected interviews of operating and operations support
personnel;
4. Facility safety documentation is in place that describes the "safety envelope" of the facility. The
safety documentation should characterize the hazards/risks associated with the facility and should
identify mitigating measures (systems, procedures, administrative controls, etc.) that protect workers
and the public from those hazards/risks. Safety systems and systems essential to worker and public
safety are defined and a system to maintain control over the design and modification of facilities and
safety-related utility systems is established;
5. A program is in place to confirm and periodically reconfirm the condition and operability of safety
systems, including safety related process systems and safety related utility systems. This includes
examinations of records of tests and calibration of safety system and other instruments which monitor