DOE-STD-3006-95
the necessary approved requirements documentation is in place and that procedures, personnel, and
equipment and systems support the approved requirements. It is not the responsibility of the ORR
team to approve the foundation documentation--only verify that it is approved and that it has been
implemented. Critical to a determination of the facility's compliance with DOE Orders and
requirements is verification that a review of the facility's conformance to applicable DOE Orders and
requirements has been performed and non-conformance issues addressed.
The breadth of the ORR will include the minimum core requirements provided in DOE 0 425.1. The
depth of the evaluation of core requirements will be determined according to the situations associated
with the shutdown and subsequent outage, magnitude of hazard, and level of complexity associated
with the proposed facility operating mode through use of the graded approach.
This standard also contains procedures and guidance for Readiness Assessments as well as conditions
and expectations for situations where exemption from Order requirements may be appropriate.
Sections 5.10 and 5.11 contain specific discussions on these alternative methods for verifying
readiness to commence program work.
4.2 Requirements. The following describes the sequence of events and decisions when an ORR is
required as part of the startup of new nuclear facilities or restart of an existing nuclear facility. The
criteria in DOE 0 425.1 define when an ORR is required as well as the approval authority for a new
start or restart activity.
4.2.1 Determination of ORR Requirements. Periodically (quarterly or as required by Operations
Office procedures) each responsible contractor should be required to identify all facility new start and
restart activities planned for the future and propose those which will require an ORR, both DOE and
responsible contractor. The responsible contractor will also propose the approval authority for each
new start and restart action. For those startups or restarts that contractor management considers do
not require an ORR, the method of readiness verification should be specified and justification for the
proposed course of action provided. The report from the responsible contractor is known as the
startup notification report.
16