The DOE Operations Office will review the responsible contractor's proposal and recommend
approval or modification to Headquarters who will approve or, modify and approve, the contractor's
proposal. Once approved by Headquarters, the contractor's proposal will be provided to the
contractor for action and to appropriate internal and external oversight agencies for their information.
4.2.2 Responsible Contractor's ORR Plan-of-Action. Four to six months before the projected
date for the contractor's ORR, the contractor will prepare and submit for approval the ORR plan-of-
action. In the event the requirement for an ORR is identified less than four months before the
estimated start, the ORR plans-of-action must be expeditiously developed, reviewed, and approved so
that the ORR schedule is maintained. The plan-of-action will provide the proposed ORR breadth
(Sections 5.1.7 and 5.9.1 discuss methods for breadth definition), the prerequisites for starting the
ORR, ORR schedule including estimated start date and duration, the proposed ORR team leader, and
any other information required by DOE 0 425.1 and information unique to the proposed ORR. The
responsible contractor's submitted ORR plan-of-action will be reviewed by the Operations Office
manager or designee and approved or forwarded to the designated approval authority with a
recommendation for approval. A copy will be sent to the Office of Environment, Safety and Health
(EH) for review and comment as well. The designated approval authority will approve the
contractor's plan-of-action and return it for execution with copies to appropriate internal and external
oversight organizations.
4.2.3 DOE ORR Plan-of-Action. Following receipt of the responsible contractor's plan-of-action,
the Operations Office management organization will prepare the DOE ORR plan-of-action. The DOE
ORR plan-of-action will include in the breadth all areas appropriate to the responsible contractor
plan-of-action plus a thorough review of the DOE management organization for capability to oversee
the facility operations to be started. The DOE ORR plan-of-action will include prerequisites, team
leader designation, breadth of the DOE ORR (Section 5.4 and Appendices 1 through 3 provide
additional details on determination of the breadth), estimated schedule and duration, and additional
information required by DOE 0 425.1. The DOE ORR plan-of-action will be formally transmitted via
management to the appropriate approval authority with a copy to EH for review and comment. Once
approved, the DOE ORR plan-of-action is provided to appropriate oversight organizations.