| DOE-EM-STD-5505-96
APPENDIX G
SAMPLE OPERATIONS ASSESSMENT REPORT
FINDING:
Fifteen of the 16 identified temporary modifications listed in the Operations Modification Log are
greater than 90 days old. (References: 1, 3, 5) [Concern: 3]
FINDING:
Documentation does not exist to officially extend temporary modifications beyond the 90 day
limit. (References: 1, 3, 5) [Concern: 3]
FINDING:
Three active temporary modifications identified in the JCS are not listed in the Operations
Modification Log. (References: 1, 4, 5) [Concern: 3]
FINDING:
The review of temporary modifications is not performed as required by the facility procedure.
(References: 1, 5) [Concern: 3]
FINDING:
Four items in building 2 had expired calibration or functional stickers affixed to them. (References
1, 5)
DISCUSSION: Items included the following:
- FRC 28 position indicator on control panel due 5/95. This calibration sticker has the
wrong due date. It should be 11/28/96.
- Magnehelic DP1-7 in ventilation duct due 1/90. This calibration was verified not required
by OSR or OSD.
- Gage P1-SW-3 on safety shower due 6/92
LOCKOUTS AND TAGOUTS
REFERENCES:
1. DOE 5480.19, Chapter IX
2. CM-4-3, Industrial Safety Manual, Volume 1, G-1
3. IP-0842 Volume II Section 4.9.1