DOE-STD-7501-99
1.3
Scope
1.3.1
Purpose
The Department of Energy expects all individuals performing DOE work to make decisions and
execute their work based on the best available information. Managers at all levels of the agency
and throughout the contractor community are expected to ensure that decision making is founded
on the best professional and industrial practices currently available. All professional, technical and
craft personnel are expected to plan and execute their work based on best available practices.
Through their work experiences all personnel are expected to identify opportunities for improvement
and best practices and share these with their local and professional colleagues, the broader DOE
community, and other federal agencies and contractors. The purpose of lessons learned is to
share and use knowledge derived from experience to: 1) promote the recurrence of desirable
outcomes, or 2) preclude the recurrence of undesirable outcomes. This technical standard is
designed to facilitate the sharing of information across the DOE complex -- among operations and
area offices, field and headquarters elements, and Federal contractor and subcontractor entities.
The standard establishes broad management expectations for developing, sharing and using
lessons learned and a framework to facilitate implementing these expectations.
Applicability
1.3.2
This technical standard defines the expectations and framework for identifying, sharing and using
lessons learned. When selected for use, this technical standard applies to all DOE Headquarters
and field organizations, management and operating contractors, and laboratories (hereafter
referred to collectively as "DOE organizations").
DOE expects each DOE element and each contractor to tailor lessons learned activities based on
the work and organizational complexity at each local level. DOE expects that the programmatic
aspects of identifying, sharing, and using lessons learned will be developed to support each local
ISMS description and the specific work of the organization(s). Requirements in the Department of
Energy Acquisition Regulations (DEAR 48 CFR 970.5204-2) for ISM Feedback and Improvement
functions are the governing requirements for contractor lessons learned programs. Also the
DEAR, 48 CFR 970.5204-2 (d) and (e), requires DOE and contractor actions to continuously