Page Title: DOE Response to Contractor's ORR Startup Notification Report
Back | Up | Next

Click here for thousands of PDF manuals

Google


Web
www.tpub.com

Home

   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Logistics
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
   
   

 



DOE-STD-3006-2000
circumstances, that delegation should be specified in the implementing procedures to be provided by
formal letter or memorandum.
5.2.2 DOE Response to Contractor's ORR Startup Notification Report. DOE Operations Office
management should review and forward the report to the Secretarial Officer via Headquarters
management. The forwarding endorsement should recommend approval or changes to be included prior
to approval.
C
Each periodic SNR should be reviewed and approved by DOE Field Office Management. In those
cases when the startup authority resides with the PSO, the Field Office Management should comment
and make a recommendation regarding approval. This assures agreement at the appropriate level for
the startup decision, thus reducing the possibility of last minute changes of direction, which are quite
costly.
C
Each periodic SNR, including the Field Office comments and actions, should be forwarded to the
cognizant PSO and site LPSO. This provides the information necessary for the PSO, LPSO, and
EH-2 to execute their respective oversight functions.
C
Contractor readiness review action to start or restart operations should not commence until the DOE
startup or restart authority has approved the proposed readiness review process.
5.2.3 DOE Review and Approval of Contractor's ORR Plan-of-Action. Review and approve, or
review and forward for approval, the responsible contractor's ORR plan-of-action.
5.2.4 DOE Prepares the ORR Plan-of-Action. Prepare the ORR plan-of-action for each nuclear
facility new start and restart for which an ORR is required. The responsible contractor's ORR plan-of-
action or the approved restart plan (when utilized) should provide the starting point for the DOE ORR
plan-of-action. The DOE plan-of-action should include prerequisites that assure readiness of DOE
programs and personnel to oversee contractor operation. When a DOE RA is required, DOE must also
prepare a properly scoped plan-of-action.
5.2.5 DOE ORR Preparation Support. Support preparation of the DOE ORR in accordance with the
provisions of the ORR plan-of-action. If the ORR Team Leader is from the Operations or Area Office,
30