| DOE-STD-3006-2000
support the preparation and planning for the ORR including preparation of the DOE's ORR
Implementation Plan. Provide support for conduct of DOE ORRs.
5.2.6 DOE Oversight of Contractor Activities. Provide day-to-day oversight of the responsible
contractor's activities to achieve and verify readiness to conduct operations including review of the
contractor ORR report and prestart finding closure plans and closure documentation. Through this day-
to-day oversight, the Operations Office management is able to provide knowledgeable recommendations
concerning responsible contractor's actions and proposals.
5.2.7 DOE ORR Preparation. Support the preparation and self assessment of the DOE Operations
Office and Area Office programs and personnel as required by the approved DOE ORR plan-of-action
and DOE ORR Implementation Plan. Achieving readiness for DOE to oversee contractor operations is
an important action necessary to support contractor startup.
5.2.8 DOE Review of Contractor's Readiness to Proceed Memorandum. Review and take
appropriate action on the responsible contractor's Readiness to Proceed Memorandum. If the Operations
Office manager is the authorization authority, he or she grants authority to conduct the DOE ORR. For
other new starts and restart, when satisfied of the readiness of the facility and the readiness of the
Operations Office management personnel and procedures to oversee contractor activity, the Readiness to
Proceed Memorandum is forwarded to Headquarters recommending the DOE ORR be started.
5.2.9 DOE Endorsement Expectations. DOE line management responsible for oversight of
contractor operations should prepare an endorsement to the Readiness to Proceed Memorandum as a part
of forwarding it to the restart authority. The DOE line management endorsement should discuss two
important elements:
C
DOE line management assessment of the readiness of the contractor to commence operations.
This assessment should be based on the day-to-day observation of contractor activities and an
assessment of the adequacy of the contractor ORR and corrective actions.
C
Readiness of DOE line management to oversee contractor operations following startup including
meeting prerequisites and core requirements in the DOE POA. The basis for the conclusion,
including the results of any DOE line management self-assessments conducted in anticipation of
startup should be included in the endorsement.