| DOE-STD-3006-2000
A. Identification of facility management observers necessary for initial operations oversight.
(1) List the management personnel assigned for initial operational evaluations of the graded
operations testing, including summary level duties, responsibilities, and shift staffing
requirements. (Specific duties and responsibilities should be listed in the remaining sections of
the plan). Include the specific duration of the initial operational evaluations. Include the specific
qualifications of each individual (resumes).
B. Equipment operability
(1) Identify and describe the integrated tests planned and required to confirm operability of
equipment during initial operations. Include the purpose and a summary of the acceptance criteria
of the tests.
(2) List management responsibilities for approval of test commencement and management
observer oversight of test performance. Include management approval requirements for key events
or progression to the next phase of testing.
(3) Provide a summary level schedule that clearly illustrates the systematic approach to full
operations.
C. Procedure viability
(1) Identify and describe the mechanism for verification of the viability of procedures during
actual performance, including requirements for management observer participation in the first time
execution of procedures.
(2) Summarize the process for procedure changes as a result of identification of inadequacies in
the field. Include any provisions for increased procedure revision support during periods of high
levels of first time execution of procedures.
D. Operator Performance
(1) Identify and describe the mechanism for real time in-plant management observer evaluation of
operator performance to verify the adequacy of operator training.
(2) Identify and describe the mechanism established for remediation of any identified weaknesses.
Appendix 3-5
|