Click here to make tpub.com your Home Page

Page Title: Summary
Back | Up | Next

Click here for thousands of PDF manuals

Google


Web
www.tpub.com

Home

   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Logistics
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
   
   

 



DOE-STD-3006-2000
number of open items at the time the Readiness to Proceed Memorandum is submitted to DOE the initial
conclusion is that the responsible contractor's management and ORR processes were not successful.
The following discussion concerning the acceptability of the open prestart items at the time the
Readiness to Proceed Memorandum is provided:
a. Each open item prerequisite to commencing facility operations must be identified as a part of the
Readiness to Proceed Memorandum.
b. The number of open items must be small. In determining how many open items is acceptable, one
principle should be that every area to be evaluated by the DOE ORR must be sufficiently complete to
permit evaluation. For example, a single finding or multiple findings that in aggregate mean that
some key program has not yet been developed and put in place would not be acceptable since the
DOE ORR would be unable to review the adequacy of the program. Only if that program were to be
in place prior to the end of the ORR would a finding of this sort be acceptable as an open item in the
Readiness to Proceed Memorandum.
c. Each open item must be defined with an explicit corrective action plan. Open items such as "the
required environmental permits have not been requested or approved" would not be acceptable in that
many additional facility procedures and activities are potentially dictated by the corrective actions to
the identified open item.
d. Each open prestart item from the contractor ORR must have a reasonable plan of corrective action in
place. The plan must be included with the identified open items in the Readiness to Proceed
Memorandum. The schedule for completion of the corrective action plan must be consistent with the
timing for the completion of the DOE ORR.
In summary, the open items should be few in number, well defined with a well defined corrective action
plan, able to be completed on a schedule which is consistent with the DOE ORR schedule, and not of
such a nature individually or in aggregate to preclude an adequate review by the DOE ORR of any
specific area.
58


Privacy Statement - Press Release - Copyright Information. - Contact Us

Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business