| DOE-HDBK-3012-96
APPENDIX 2
SITE CONTACT MEMORANDUM
Refer to the Plan of Action.
Operations Office or Area Office Manager
Operational Readiness Review of
[Facility] .
An Operational Readiness Review (ORR) of [Facility] will be performed. [Site point-of-
contact] has been identified as the lead Department of Energy contact at the site. [Team Leader]
will lead the review team.
Enclosed are a preliminary schedule for the overall review and a detailed schedule for the onsite
portion, an agenda for the pre-review visit, a list of support required for the onsite portion of the
review, a list of site documents required to prepare the team for the review, and an ORR summary
document. Please forward one copy of each requested document to [Team Leader] by [Date] .
Please contact [Team Leader] (phone #) if you wish to discuss these items or any other aspect of
the review.
Your assistance is greatly appreciated.
Team Leader
Attachments
cc w/Attachments:
Manager, Area Office
Program Office Director
Facility Manager
_______________________________________
*Attachments
ORR Logistics (Appendix 3)
ORR Review Schedule (Appendix 4)
ORR Previsit Schedule (Appendix 5)
APPENDIX 2-1
|
Privacy Statement - Press Release - Copyright Information. - Contact Us |