| DOE-HDBK-3027-99
XYZ 6 The same as XYZ 2 except that radiological controls are satisfactory. Your review need
not go beyond a general review of radiological controls.
XYZ 7 The same as XYZ 4 except that the RCRA compliance inspection identified several areas
of concern. The scope of the verification for XYZ 7 should therefore, include a follow up
of the issues identified during the RCRA inspection.
XYZ 8 XYZ 8 is a new facility that will be starting operations within one month. It is a Hazard
Category 2 facility. An ORR will be conducted to authorize the start of operations.
Therefore, only those aspects of the ISMS for XYZ 8 that are outside of the scope of
the ORR should be included. These include programmatic and budgetary control
procedures that were identified in the ISMS.
The following special considerations apply to the Phase II ISMS verification for the infrastructure
programs, which are described as follows:
Maintenance: The ISMS Description indicates that the site maintenance program is mature and
will be continued across XYZ. A recent Headquarters' Maintenance evaluation determined the
program was satisfactory. Therefore, the verification need not include a review of the
maintenance program except for XYZ 4.
Emergency Preparedness : Same as Maintenance.
Radiological Controls : Recent staff assessments, as well as the contractor's self assessments and
recent occurrence reports, raise questions as to the adequacy of the radiological controls program
at XYZ. Consequently, the scope of this Phase II ISMS verification should include a thorough
review of the radiological controls program at XYZ as well as the implementation of radiological
controls procedures within each facility at XYZ.
DOE Implementation of ISMS : The scope of your review should include verifying that the ISMS
responsibilities for my staff have been implemented. These responsibilities are defined in the
Manual of Safety Management Functions, Requirements, and Authorities (FRA).
The review should be limited to the implementation aspects of the XYZ ISMS including:
C preparation and approval of mission assignments and program guidance,
C allocation of adequate resources to support the mission and safety responsibilities,
C approval of hazards analysis and identified controls,
C adequacy of guidance provided to staff regarding the safety management system, and
C participation of staff in feedback and improvement mechanisms including verifying
contractor performance and evaluating the performance of the ISMS.
A-4-8
|
Privacy Statement - Press Release - Copyright Information. - Contact Us |