Page Title: Format for data recording of individual action step showing sign off by initials
Back | Up | Next

Click here for thousands of PDF manuals

Google


Web
www.tpub.com

Home

   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Logistics
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
   
   

 



DOE-STD-1029-92
[1]
Provide appropriate space or tables for entering data (either in the procedure or in
data sheets).
[2]
If the condition to be verified or checked is not found, provide the appropriate
actions to take.
[3]
Include labeled lines in action steps as necessary for users to record required
information.
EXAMPLE 4-15. Format for data recording of individual action step
showing sign off by initials.
[10]
Record cooling water flow to Cylinder 12 Cooling Jacket.
Required GPM
Actual GPM Initials and date
[4]
Specify required independent verification and inspection action steps (the number
of independent verification and inspection action steps increase as the
consequences of performance error increase).
[5]
Include directions for notifying other personnel as discrete action steps. Actions
requiring notifications of others often include
C System alignments to be performed.
C Systems to be removed from or returned to service.
C Alarms and alarm setpoints that may annunciate as a result of performing the
procedure.
C Equipment actuations that are expected to occur during performance of the
procedure.
C Actions with electrical or mechanical interlocks involved (e.g. interlocks to be
honored or overridden).
C The effects of precautions and limitations on the operating conditions, noting
which equipment will be inoperative and which lights, alarms, or annunciators
will react.
47