Ensure that range and accuracy of measuring equipment are consistent with the
expected values to be measured.
[12]
Determine when data concerning test equipment (for example, serial numbers or
calibration dates) must be recorded. Provide space in the procedure or in an
appendix to record the data before the user encounters action steps which use the
test equipment for critical measurements.
[13]
Specify verification and performance checks or special controls required before the
equipment is used. If the performance check is done just before use, include the
check in the body of the procedure rather than in the prerequisite actions section.
EXAMPLE 3-16. Measuring and test equipment identification.
[3]
Obtain two stopwatches (calibrated and approved by Quality Assurance Lab), and complete
Table 4-2.
TABLE 4-2
M&TE No.
Expiration Date
Performer Initials
3.5.4 Field Preparations
[1]
Provide instructions for preparatory field activities that must be completed before
continuing with the procedure. Examples of these activities are listed below.
C Lock-out/tag out of equipment
EXAMPLE 3-17. Tag out action step.
[4]
Verify that the GM Diesel unit to be inspected has been tagged out.