| DOE-STD-1029-92
[1]
Organize activities in the order that they will be performed.
[2]
Divide the performance sections into subsections that logically group related
activities as established in the procedure basis outline.
[3]
Use headings for each subsection that reflect the activity rather than a generic title
(for example, "Removing the Actuator," rather than "Actuator").
[4]
Write the specific action steps within the performance sections in accordance with
Section 4 of this guide.
3.7
Post-performance Activity
The post-performance activity section stipulates actions needed to close out the activity
including testing, restoration, and compiling results.
3.7.1 Testing
[1]
If operability of equipment has been affected while performing a procedure and
operability has to be verified before returning the equipment to service, include
action steps that specify these tests.
3.7.2 Restoration
[1]
Provide action steps to specify and record the return of all affected structures,
systems, or equipment to the desired configuration.
[2]
Include instructions for
C Required restoration adjustments, storage, or maintenance of laboratory and
process equipment
C The return of tools and equipment
C The proper disposal or storage of consumables such as test samples or
chemicals not used in the process.
[3]
Provide space for recording the notification of appropriate personnel that the
system has been returned to service.
[4]
Include provisions for close out of any permits (such as confined entry permits)
that were required to perform the procedure.
[5]
Provide for verification of appropriate restoration action steps.
33
|