| DOE-HDBK-XXXX-2005
06/30/2005
(ii)
A concise statement of the basis for the determination;
(iii) Any remedy, including the amount of any civil penalty;
(iv) A statement explaining the reasoning behind any remedy; and
(v)
If the Notice assesses a civil penalty, notice of respondent's right:
(A)
To waive further proceedings and pay the civil penalty;
(B)
To request an on-the-record adjudication of the assessment of the civil
penalty; or
(C)
To seek judicial review of the assessment of the civil penalty.
[10 CFR 820.2]
236.
FINAL ORDER. An order of the Secretary that represents final agency action and,
where appropriate, imposes a remedy with which the recipient of the order must comply.
[10 CFR 820.2]
FINAL SAFETY ANALYSIS REPORT (FSAR). The Safety Analysis Report (SAR)
237.
submitted to and approved by DOE prior to the authorization to operate a new nuclear
facility or that documents the adequacy of the safety analysis for an existing nuclear
facility. (See Preliminary Documented Safety Analysis, Preliminary Safety Analysis
Report, Safety Analysis Report, Safety Basis, Safety Evaluation, and Safety Evaluation
Report)
FIRE AREA. A location bounded by construction having a minimum fire resistance
238.
rating of 2 hours with openings protected by appropriately fire-rated doors, windows,
dampers, or penetration seals. The boundaries or exterior fire areas (yard areas) or other
locations that represent unique conditions should be as determined by the cognizant fire
protection engineer (contractor or DOE). [DOE-STD-1066-97]
239.
FIRE BARRIER. A continuous membrane, either vertical or horizontal, such as a wall or
floor assembly that is designed and constructed with a specified fire resistance rating to
limit the spread of fire and that also will restrict the movement of smoke. Such barriers
may have protected openings.