| REACTOR AREA PRACTICAL FACTORS CARD
NAME: _____________________________________________________________
Instructions: The trainee must perform, simulate, or observe (as required and indicated by the X's) all practical factors listed
on this card. Activities indicating a single NPPO action may not be changed: activities indicating more than one NPPO
action (perform, simulate, observe) may be satisfied by completing any one. The order of preference for the actions shall be
(1) perform, (2) simulate, (3) observe.
Upon satisfactory completion of each activity, a qualified operator shall circle the action taken, and sign (using full signature)
and date in the appropriate space.
S
P
i
O
e
m
b
r
u
s
f
l
e
o
a
r
r
t
v
FUNCTIONAL LOGS
m
e
e
Signature
Date
Complete Log 1-A (Section 2)
X
Complete Log 1-A (Section 4)
X
Complete Log 1-A (Section 5)
X
Complete Log 1-A (Section 8)
X
Complete Log 1-A (Section 9)
X
Complete Log 1-C
XX
Complete Log 7-A
X
Complete Log 7-M
X
Complete Log 7-S
X
Complete Log 8-T
X
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
Participate in reactor startup or restart
XXX
Perform reactor startup or restart
X
Participate in reactor shutdown (anticipatory)
XXX
Perform reactor shutdown (normal)
X
Plot CO/CN during startup
X
Perform control-rod rebank
X
Complete ascending PRD calculation
X
Participate in reactor interlock checks (at console)
X
Participate in fuel-handling interlock checks (at console)
X
Complete reactivity plot calculation
X
Compute reactor MWhr
X
Complete control-rod calibration
X
Perform rod drops at power
XX
Complete calorimetric determination of power (Log 7-B)
X
Complete CO/CN plots during unrestricted fuel handling
X
Perform control-rod comparison without use of DAS
X
Calculate reactor 60-s period
X
Calculate critical rod position for reactor restart, then 60-s
period
X
I hereby verify that the named individual has satisfactorily completed all reactor-area practical factors and has demonstrated
the necessary abilities and maturity to perform the indicated activities.
_______________________________________________________________
Alternate Reactor Shift Supervisor
Date
B-9
|