| DOE-STD-1082-94
All reviewers shall expedite their reviews to allow closure on an acceptable
implementation plan as early as possible.
5.1.5.2 Delegated Approval Authority for Implementation Plans. The
CSO may delegate the authority to approve specific implementation plans. Any
such delegation shall be provided in writing to the designee.
The Operations Office point-of-contact is responsible for identifying to the
affected CSOs any implementation plans which are based upon previously
approved implementation plans and do not involve (1) additional funding
commitments, (2) commitment schedule changes, (3) new programmatic
impacts, or (4) exemptions from the requirements. These implementation plans
will typically be new plans for nuclear safety rules which were preceded by DOE
Orders on the same subject or revisions to previously approved plans. Typically,
the review and approval authority for these plans will be delegated to the
Operations Office by the CSO.
Wherever the authority to approve an implementation plan has been delegated
to the Operations Office by all of the affected CSOs, the Operations Office may
choose to have the Review Team consist entirely of Operations Office personnel
provided any technical and programmatic requirements can be handled by the
designated team.
The authority to approve exemptions to rules cannot be delegated.
5.1.6 Approval.
5.1.6.1 Approval Recommendations by the Review Team. The Review
Team Leader is responsible for ensuring that the Operation's Office Manager
receives the Review Team's final recommendation for approval no less than five
weeks prior to the approval date specified in the DOE requirements document.
That recommendation shall either endorse acceptance of the implementation
plan as submitted (or changed through negotiations during the review process)
or, if issues cannot be resolved with the implementing organization, provide
19
|