DOE-STD-1082-94
approval of implementation plans which involve additional funding needs.
Following approval of the implementation plans, DOE has a responsibility to
provide appropriate funding to support approved activities and schedules. If
funding is subsequently unavailable when needed to support the implementation
plan schedules, the implementation plans should be revised to reflect the new
schedules supported by funding (provided any schedules specifically prescribed
in the DOE requirements documents are met or schedule exemptions are
approved). Such revisions shall be submitted to DOE for review and approval.
Alternatively, implementing organizations may consider requesting an exemption
for unfunded activities, if the criteria for granting an exemption are met (see
Section 3.11 of this technical standard).
3.11 Exemptions. Exemptions are to be requested whenever relief is
sought from an applicable DOE requirement. The implementation plan shall
clearly identify any exemptions that have been approved or are being requested
from the subject requirements. Implementing organizations may submit
requests for exemptions as part of the implementation plan provided that they
relate to the same requirements. Requests for exemption that are submitted as
part of the implementation plan shall be identified in the implementation plan
summary for early recognition. Early identification of exemption requests is
important because they may need to follow a separate review and approval
process.
The provisions for requesting and granting exemptions to rules are stated in 10
CFR Part 820, Subpart E, "Exemption-Relief." All exemptions to rules must be
approved by the Secretarial Officer designated in 10 CFR Part 820,
Subpart E notwithstanding the level of approval delegated for the
implementation plan. The provisions for granting exemptions to Orders,
Notices, Immediate Action Directives and Manuals are specified in the
directives documents.
3.12 Compensatory Actions. The implementation plan shall include a
description of any compensatory actions that will be adopted prior to full
implementation of the requirements. Compensatory actions are temporary
11