DOE-STD-1082-94
used to develop the proposed schedules and shall be sufficiently flexible to
accommodate changes at later dates.
The prioritization process shall consider available information from safety
analyses and other sources and give primary attention to controlling and
reducing risks to the public, the environment, and the workers to an
acceptable level. It should also consider other factors such as mission needs,
outage schedules, and external regulations.
The prioritization process should be selected in consultation with the
applicable DOE Operations Office and Program Offices to ensure that the
prioritization of efforts meets DOE expectations. In order to tie budgets to
schedules, priorities should be determined in accordance with the DOE
Environment, Safety, and Health (ES&H) Management Plan wherever
budgets are determined on the basis of that plan. For other facilities, the use
of the ES&H Management Plan process or a compatible process is
encouraged in determining the priorities.
3.10 Milestones and Schedules. The implementation plan shall identify
proposed milestones with achievable schedules developed in accordance with
the additional activities and the prioritization process identified in the plan
(see Sections 3.6 and 3.9 above). In developing the schedules, the
implementing organization shall consider the resources available to support
the work, as well as any major work reductions or schedule changes in other
areas that will be required in order to meet the proposed schedules. The
implementation plan shall identify major impacts to activities or commitments
outside the scope of the plan which will be caused by the proposed additional
activities.
Schedules shall be developed using the best information available with any
assumptions on availability of resources (monetary or non-monetary) clearly
stated. The milestones and schedules will be enforceable commitments upon
approval of the plan. Schedule commitments must be firm commitments and
consequently, shall not be listed as contingent on funding. Thus, it is
essential that line program representatives participate in the review and
10